SUBSECRETARIA DE INFRAESTRUCTURA
DIRECCION GENERAL DE CONSERVACION DE CARRETERAS
Programa Nacional de Conservación de Carreteras
Avance Físico - Financiero
JUNIO 2021
No. NOMBRE DE LA OBRA UBICACIÓN META ASIGNACIÓN AVANCE FÍSICO AVANCE FINANCIERO %
Km inicial Km final UNIDAD %
ZACATECAS 194,000,000.00 43.93 47.28
Conservación Periódica 59.70 49,238,008.29 39.55 58.34 60.24
Microcarpeta de 3.0 cm 27.00 19,286,835.63 18.55 69.03 69.03
1 Lim. de Edos. Jal./Zac. - Lim. de Edos. Zac./Jal. 120.00 129.00 9.00 6,554,277.81 9.00 100.00 100.00
2 Lim. de Edos. Jal./Zac. - Lim. de Edos. Zac./Jal. 211.00 219.00 8.00 5,810,649.61 4.37 54.63 54.61
3 Lim. Edos. Jal./Zac. - Malpaso 77.00 87.00 10.00 6,921,908.21 5.18 51.80 51.80
Riego de Sello 8.70 5,030,277.68 7.25 83.36 83.36
4 Fresnillo - Valparaiso 64.00 72.70 8.70 5,030,277.68 7.25 83.36 83.36
Renivelaciones aisladas y Riego de Sello 2,260,661.58 100.00
FINIQUITOS finiquito 2,260,661.58 100.00
Microaglomerado 24.00 22,660,233.40 13.75 43.69 43.67
5 Lim. Edos. Jal./Zac. - Zapoqui (Cpo.A) 283.00 292.00 9.00 6,371,013.78 9.00 100.00 100.00
6 Lim. Edos. Jal./Zac. - Zapoqui (Cpo.B) 283.00 292.00 9.00 6,332,021.24 2.83 31.44 31.43
7 Ent. Chicharrona - Sombrerete 164.00 170.00 6.00 4,806,619.12 1.92 32.00 31.95
SALDO SM 5,150,579.26 0.00
Conservación Periódica de Puentes 7.00 4,420,000.00 3.00 42.86 65.27
Conservación Periódica de Puentes 7.00 4,420,000.00 3.00 42.86 65.27
Puntos de conflicto 1.00 13,000,000.00 0.60 60.00 49.26
8 Villanueva - Tabasco 184+500 - 190+500 1.00 8,806,142.48 0.60 60.00 72.72
SALDO SM 4,193,857.52 0.00
Conservación Rutinaria de Tramos 1,482.80 89,500,000.00 618.47 44.31 51.00
Conservación Rutinaria de Tramos 1,482.80 75,447,319.36 618.47 59.76
Zona 1 0.00 4,499,968.33 29.19 20.45 38.66
Zona 2 3,997,973.40 36.05 20.41 40.83
Zona 3 3,997,799.06 39.05 21.77 36.36
Zona 4 3,498,666.08 43.03 25.46 50.93
Zona 5 3,808,085.46 68.33 39.49 43.26
Zona 6 3,763,758.39 67.17 37.40 44.60
Zona 7 3,800,594.62 63.55 36.37 44.09
Zona 8 3,898,865.18 69.04 45.12 73.60
Zona 9 3,691,498.65 19.88 16.68 35.35
Zona 10 3,982,889.17 40.92 27.91 33.75
Zona 11 4,296,128.42 56.35 36.32 36.32
Zona 12 3,906,607.92 59.80 41.01 41.01
Zona 13 3,992,781.47 26.11 17.80 27.83
Zona 1 2,396,400.12 86.10 28.27 73.81
Zona 2 2,635,737.62 199.90 54.26 100.00
Zona 3 3,387,230.45 275.27 95.44 100.00
Zona 4 3,496,607.74 222.93 93.28 100.00
Zona 5 2,288,917.13 114.40 52.33 100.00
Zona 6 2,397,219.84 147.38 69.90 100.00
Zona 7 2,939,303.42 113.50 74.87 100.00
Zona 8 2,767,624.35 136.50 94.01 100.00
Zona 9 2,002,662.54 127.00 100.00 100.00
SALDO SM 9,052,680.64 0.00
Gastos de Operación 5,000,000.00 11.27
Señalamiento Horizontal 2,050.03 15,780,000.00 0.00 0.00 18.53
Señalamiento Horizontal 633.68 5,260,000.00 0.00 0.00 15.57
Señalamiento Horizontal 641.72 5,260,000.00 0.00 0.00 13.07
Señalamiento Horizontal 774.63 4,550,861.48 0.00 0.00 15.58
Señalamiento Horizontal finiquito 709,138.52 100.00
Señalamiento Vertical 1,314.00 5,000,000.00 263.00 20.02 18.66
Señalamiento Vertical 657.00 2,500,000.00 263.00 40.03 20.36
Señalamiento Vertical 657.00 2,500,000.00 0.00 0.00 16.95
Barreras de Protección 8,130.00 5,864,991.71 0.00 0.00 0.00
Barreras de Protección 8,130.00 5,864,991.71 0.00 0.00 0.00
Conservación Rutinaria de Puentes 311.00 5,697,000.00 118.00 37.91 32.70
Conservación Rutinaria de Puentes 150.00 2,276,175.72 58.00 38.67 38.42
Conservación Rutinaria de Puentes 161.00 2,662,735.97 60.00 37.27 37.12
SALDO SM 758,088.31 0.00
Otros Subprogramas 5,500,000.00 25.51
Seguimiento 2,158,070.17 33.60
Seguimiento 2,073,264.78 32.69
Seguimiento (SALDO) 1,268,665.05 0.00

Versión PDF



Actualizada al 23/Jul/2021, 01:31