No. NOMBRE DE LA OBRA UBICACIÓN META ASIGNACIÓN AVANCE FÍSICO AVANCE FINANCIERO %
Km inicial Km final UNIDAD %
  OAXACA       378,000,000.00   57.74 47.75
                 
  RECONSTRUCCIÓN       11,715,458.71   83.97 88.49
                 
  Reconstrucción de Puentes     1.00 11,715,458.71 1.00 93.27 88.49
1 El Gramal (Oaxaca - Tehuantepec) 125+900 1.00 9,837,293.43 1.00 100.00 98.16
  FINIQUITOS     finiquito 710,293.03     100.00
  SALDO     SM 1,167,872.25     0.00
                 
  Conservación Periódica     94.10 120,269,613.33 35.13 58.61 38.35
                 
  Recuperacion de pavimento y Carpeta de 5.0 cm     9.00 40,287,221.10 4.10 46.94 21.25
2 Huajuapan de León - Llano Verde (ALTO DESEMPEÑO) 0.00 4.00 4.00 12,146,071.93 1.60 40.00 20.00
3 Oaxaca - Puerto Angel (ALTO DESEMPEÑO) 36.00 41.00 5.00 27,510,593.71 2.50 50.00 20.00
  Ajustes de Costos     finiquito 630,555.46     100.00
                 
  Microcrapeta     4.70 12,548,476.91 2.54 54.00 20.00
4 Oaxaca - Tehuantepec (Cpo. B) SMA 8.50 13.20 4.70 12,548,476.91 2.54 54.00 20.00
                 
  Renivelación y Riego de Sello     80.40 61,827,725.14 28.49 64.64 50.18
5 Oaxaca - Tehuantepec 150.00 167.00 17.00 21,853,922.63 12.41 73.00 41.81
6 La Ventosa - Tehuantepec (Ramal a Ixtaltepec) 0.00 10.40 10.40 15,492,703.21 10.40 100.00 100.00
7 Huajuapan de Leon - Llano Verde 42.00 50.00 8.00 11,998,349.63 5.68 71.00 53.30
8 Lim. de Edos. Ver/Oax.-La Ventosa (T.A.) 154.00 195.50 30.00 6,482,749.67 0.00 0.00 0.00
9 Oaxaca - Barranca Larga 40.00 55.00 15.00 6,000,000.00 0.00 0.00 0.00
                 
  Obras de Drenaje     1.00 1,174,631.50 0.60 60.00 20.00
10 Lim. De Edos. Ver/Oax.-La Ventosa 235+650   1.00 1,174,631.50 0.60 60.00 20.00
                 
  Atención a Fallas     1.00 4,431,558.68 1.00 100.00 85.53
11 Lím. De Edos. Pue./Oax. El Chilar 113+600   1.00 4,431,558.68 1.00 100.00 85.53
                 
  Conservación Periódica de Puentes     4.00 5,109,530.90 3.40 80.46 57.03
  Conservación Periódica de Puentes     4.00 3,471,180.50 3.40 85.00 78.31
  FINIQUITOS     finiquito 195,649.75     100.00
  SALDO     SM 1,442,700.65     0.00
                 
  Conservación Rutinaria de Tramos     2,867.70 174,732,036.45 1,638.12 68.58 59.81
  Conservación Rutinaria de Tramos     2,867.70 141,909,166.91 1,638.12   55.96
  Zona 1       3,959,639.12 71.96 78.53 48.59
  Zona 2       2,879,244.35 38.32 42.58 31.56
  Zona 3       2,828,086.01 31.48 38.11 26.90
  Zona 4       2,747,127.20 77.57 73.39 65.68
  Zona 5       2,817,539.31 60.00 65.93 48.47
  Zona 6       3,146,315.97 39.94 56.90 51.93
  Zona 7       3,125,548.89 35.61 50.66 43.87
  Zona 8       2,970,398.31 34.39 35.02 30.18
  Zona 9       3,071,165.13 47.82 56.26 45.81
  Zona 10       2,690,578.65 21.79 25.64 19.71
  Zona 11       2,925,800.49 32.70 38.47 30.47
  Zona 12       2,877,536.25 44.24 50.13 36.03
  Zona 13       2,515,464.64 24.08 32.33 27.43
  Zona 14       2,641,236.89 52.83 64.51 30.42
  Zona 15       3,461,440.00 43.21 58.24 46.84
  Zona 16       2,725,104.42 44.10 56.32 49.92
  Zona 17       2,581,189.72 22.32 34.34 25.28
  Zona 18       3,729,781.12 49.20 69.40 66.73
  Zona 19       4,271,036.25 78.81 93.60 90.60
  Zona 20       2,661,715.29 57.83 64.25 57.91
  Zona 21       2,844,268.84 58.31 71.02 41.70
  Zona 22       2,472,132.96 57.79 72.69 60.02
  Zona 23       2,602,596.42 19.30 28.05 21.21
  Zona 24       3,894,830.33 66.37 65.58 55.13
  Zona 25       3,805,771.15 58.18 59.55 41.71
  Zona 26       3,998,222.00 56.39 49.16 44.07
  Zona 27       2,531,661.14 54.16 77.04 74.40
  Zona 28       2,722,949.78 57.20 77.93 47.18
  Zona 29       3,848,579.68 62.40 78.00 55.23
  Zona 30       3,947,279.09 56.53 74.74 69.63
  Zona 31       3,268,540.64 42.41 45.68 35.43
  Zona 32       3,562,425.71 49.76 58.00 36.55
  Zona 33       2,668,239.48 32.42 41.09 35.04
  Zona 34       3,221,242.34 58.68 71.56 61.66
  Zona 1       2,611,066.21 165.84 100.00 86.74
  Zona 2       2,256,690.09 172.60 100.00 100.00
  Zona 3       2,051,452.00 191.49 100.00 59.42
  Zona 4       2,051,824.36 179.30 100.00 100.00
  Zona 5       2,309,571.77 126.45 90.00 67.38
  Zona 6       2,121,042.95 183.20 100.00 46.08
  Zona 7       2,760,089.70 170.00 100.00 67.17
  Zona 8       1,634,286.59 143.29 100.00 90.62
  Zona 9       1,983,856.88 183.10 100.00 86.04
  Zona 10       1,958,423.53 171.15 100.00 100.00
  Zona 11       1,970,854.35 135.90 100.00 100.00
  Zona 12       2,480,895.07 163.70 100.00 100.00
  Zona 13       2,080,536.44 163.70 100.00 91.51
  Zona 14       2,132,460.51 194.24 91.45 75.35
  Zona 15       1,556,116.74 143.70 100.00 87.27
  Zona 16       2,040,219.60 132.29 85.00 66.18
  Zona 17       1,895,092.55 151.89 94.40 90.62
  FINIQUITOS     finiquito 25,122,869.54     99.86
  Gastos de Operación       7,700,000.00     0.00
                 
  Señalamiento Horizontal     1,828.90 35,427,877.92 203.88 10.78 20.17
  Señalamiento Horizontal     1,043.40 15,101,906.37 93.91 9.00 20.00
  Señalamiento Horizontal     785.50 13,273,621.32 109.97 14.00 20.00
  FINIQUITOS     finiquito 1,471,194.48     100.00
  SALDO     SM 5,581,155.75     0.00
                 
  Señalamiento Vertical     4,069.00 16,245,482.69 0.00 0.00 27.36
  Señalamiento Vertical     4,069.00 15,364,099.68 0.00 0.00 23.19
  FINIQUITOS     finiquito 881,383.01     100.00
                 
  Conservación Rutinaria de Puentes     542.00 6,500,000.00 325.53 60.06 42.30
  Conservación Rutinaria de Puentes     144.00 1,726,937.27 89.93 62.45 40.29
  Conservación Rutinaria de Puentes     109.00 1,307,195.57 53.19 48.80 46.55
  Conservación Rutinaria de Puentes     148.00 1,774,907.75 75.36 50.92 36.74
  Conservación Rutinaria de Puentes     141.00 1,690,959.41 107.05 75.92 46.91
                 
  Otros Subprogramas       8,000,000.00     28.19
  Seguimiento       3,768,767.50     29.17
  Seguimiento       3,712,052.19     31.15
  Seguimiento (SALDO)       519,180.31     0.00

Versión PDF



Actualizada al 23/Jul/2021, 01:31