SUBSECRETARIA DE INFRAESTRUCTURA | |||||||
DIRECCION GENERAL DE CONSERVACION DE CARRETERAS | |||||||
Programa Nacional de Conservación de Carreteras | |||||||
Cierre 2018 | |||||||
NOMBRE DE LA OBRA | UBICACIÓN | META | ASIGNACION |
AVANCE FISICO | AVANCE FINANCIERO |
||
Km Inicial | Km Final | UNIDAD | % | ||||
CAMPECHE | 775,837,310.03 | 100.0 | 100.00 | ||||
RECONSTRUCCIÓN | 114,619,911.61 | 20.30 | 100.0 | 100.0 | |||
Reconstrucción de Tramos | 15.30 | 85,136,732.74 | 15.30 | 100.0 | 100.0 | ||
Fco. Escárcega - Champotón (Fco. Escárcega - Miguel Hidalgo) | 1.70 | 4.00 | 2.30 | 12,780,746.70 | 2.30 | 100.0 | 100.0 |
Fco. Escárcega - Champotón (Miguel Hidalgo - La Esperanza) (T.A.) (1) | 6.00 | 12.50 | 5.00 | 27,541,100.26 | 5.00 | 100.0 | 100.0 |
Fco. Escárcega - Champotón (La Esperanza - Miguel Colorado) | 13.50 | 17.50 | 4.00 | 21,544,729.30 | 4.00 | 100.0 | 100.0 |
Fco. Escárcega - Champotón (Miguel Colorado - Revolución) (T.A.) (2) | 20.00 | 32.50 | 4.00 | 23,270,156.48 | 4.00 | 100.0 | 100.0 |
Reconstrucción de Puentes | 5.00 | 29,483,178.87 | 5.00 | 100.0 | 100.0 | ||
Sabancuy II, IV, V (Diaz Ordaz - Sabancuy) | 55+400 | 56+240 | 3.00 | 16,102,162.84 | 3.00 | 100.0 | 100.0 |
Champoton (Cd. del Carmen - Campeche) | 143+450 | 1.00 | 9,643,540.57 | 1.00 | 100.0 | 100.0 | |
Salto de ahogado (Ramal Calendaria) | 28+400 | 1.00 | 3,737,475.46 | 1.00 | 100.0 | 100.0 | |
Conservación Periódica | 258.60 | 458,003,803.07 | 258.60 | 100.0 | 100.0 | ||
Bacheo y Carpeta de 5.0 cm | 19.75 | 62,801,869.11 | 19.75 | 100.0 | 100.0 | ||
Isla Aguada-Champotón (T.A.) (3) | 90.00 | 96.00 | 5.00 | 18,718,808.66 | 5.00 | 100.0 | 100.0 |
Isla Aguada-Champotón (T.A.) (4) | 105.00 | 109.00 | 3.50 | 13,158,116.03 | 3.50 | 100.0 | 100.0 |
Lim. Edos. Tab./Camp-Zacatal | 149.00 | 154.00 | 5.00 | 19,281,043.52 | 5.00 | 100.0 | 100.0 |
Haltunchen - Tenabo (Haltunchen - Cayal) | 10.00 | 11.70 | 1.70 | 3,436,904.23 | 1.70 | 100.0 | 100.0 |
Haltunchen - Tenabo (Haltunchen - Cayal) | 23.45 | 28.00 | 4.55 | 8,206,996.67 | 4.55 | 100.0 | 100.0 |
Riego de Sello | 167.48 | 174,700,493.55 | 167.48 | 100.0 | 100.0 | ||
Isla Aguada - Champotón | 96.00 | 99.50 | 3.50 | 12,899,713.82 | 3.50 | 100.0 | 100.0 |
Lím. de Edos. Tab./Camp. - Fco. Escárcega (T.A.) (5) | 196.94 | 215.00 | 12.00 | 12,697,217.36 | 12.00 | 100.0 | 100.0 |
Lím. de Edos. Tab./Camp. - Fco. Escárcega | 256.50 | 260.00 | 3.50 | 12,656,575.00 | 3.50 | 100.0 | 100.0 |
Fco. Escárcega - Lim. Edos. Camp./Q. Roo | 12.50 | 18.00 | 5.50 | 4,788,646.96 | 5.50 | 100.0 | 100.0 |
Fco. Escárcega - Lim. Edos. Camp./Q. Roo | 45.00 | 56.00 | 11.00 | 9,598,479.93 | 11.00 | 100.0 | 100.0 |
Fco. Escárcega - Lim. Edos. Camp./Q. Roo | 97.50 | 106.00 | 8.50 | 7,088,826.85 | 8.50 | 100.0 | 100.0 |
Fco. Escárcega - Lim. Edos. Camp./Q. Roo | 169.65 | 173.02 | 3.38 | 4,599,999.84 | 3.38 | 100.0 | 100.0 |
Fco. Escárcega - Lim. Edos. Camp./Q. Roo | 173.02 | 176.40 | 3.38 | 4,599,999.97 | 3.38 | 100.0 | 100.0 |
Fco. Escárcega - Lim. Edos. Camp./Q. Roo | 230.00 | 233.50 | 3.50 | 12,699,106.74 | 3.50 | 100.0 | 100.0 |
Haltunchen - Tenabo (Haltunchen - Cayal) | 28.00 | 41.00 | 13.00 | 10,812,596.12 | 13.00 | 100.0 | 100.0 |
Haltunchen - Tenabo (Entr. Chencolli - Tenabo) (T.A.) (6) | 4.00 | 27.42 | 21.20 | 13,077,039.06 | 21.20 | 100.0 | 100.0 |
Ramal a Tixmucuy | 0.00 | 2.20 | 2.20 | 1,856,938.58 | 2.20 | 100.0 | 100.0 |
Campeche Umán (Campeche - Entr. Chencolli) | 12.00 | 31.12 | 19.12 | 12,956,375.31 | 19.12 | 100.0 | 100.0 |
Campeche Umán (Chencolli - Hopelchen) | 57.50 | 74.00 | 16.50 | 13,674,962.57 | 16.50 | 100.0 | 100.0 |
Campeche Umán (Hopelchen - Bolonchen) | 88.30 | 99.00 | 10.70 | 8,081,490.13 | 10.70 | 100.0 | 100.0 |
Candelaria - Nuevo Coahuila (Ramal Edo. de México - Monclova) | 0.00 | 6.50 | 6.50 | 12,891,601.55 | 6.50 | 100.0 | 100.0 |
Diaz Ordaz - Sabancuy (Chicbul - Chekubul) | 20.00 | 30.00 | 10.00 | 8,295,398.20 | 10.00 | 100.0 | 100.0 |
Diaz Ordaz - Sabancuy (Chekubul - Sabancuy) | 30.00 | 44.00 | 14.00 | 11,425,525.56 | 14.00 | 100.0 | 100.0 |
Recuperación de Acotamientos y Carpeta de 7.0 cm | 10.00 | 54,178,300.30 | 10.00 | 100.0 | 100.0 | ||
Tixmucuy - Edzna | 47.00 | 52.00 | 5.00 | 27,227,205.83 | 5.00 | 100.0 | 100.0 |
Tixmucuy - Edzna | 52.00 | 57.00 | 5.00 | 26,951,094.47 | 5.00 | 100.0 | 100.0 |
Fresado y Carpeta de 5.0 cm | 20.16 | 60,014,560.69 | 20.16 | 100.0 | 100.0 | ||
Haltunchen - Tenabo (Entr. Chencolli - Tenabo) | 0.00 | 4.00 | 4.00 | 10,219,735.19 | 4.00 | 100.0 | 100.0 |
Fco. Escárcega - Lim. Edos. Camp./Q. Roo | 56.00 | 61.00 | 5.00 | 13,299,834.30 | 5.00 | 100.0 | 100.0 |
Fco. Escárcega - Lim. Edos. Camp./Q. Roo | 176.40 | 179.90 | 3.50 | 9,849,701.11 | 3.50 | 100.0 | 100.0 |
Lim. Edos. Tab./Camp. - Fco. Escárcega (T.A.) (7) | 274.10 | 295.88 | 7.66 | 26,645,290.09 | 7.66 | 100.0 | 100.0 |
Nanosello | 39.39 | 9,905,115.70 | 39.39 | 100.0 | 100.0 | ||
Nanosello (T.A.) (8) | 39.39 | 9,905,115.70 | 39.39 | 100.0 | 100.0 | ||
Protección Marginal | 1.82 | 28,730,068.80 | 1.82 | 100.0 | 100.0 | ||
Cd. del Carmen - Champotón (T.A.) (9) | 16.55 | 109.13 | 1.00 | 15,229,428.30 | 1.00 | 100.0 | 100.0 |
Lim. Edo. Tab./Camp. - Zacatal (T.A.) (10) | 160.10 | 162.40 | 0.82 | 13,500,640.50 | 0.82 | 100.0 | 100.0 |
Estabilidad de Taludes | 3.00 | 12,029,328.98 | 3.00 | 100.0 | 100.0 | ||
Ramal Candelaria - Nuevo Coahuila (T.A.) (11) | 53.00 | 78.66 | 3.00 | 12,029,328.98 | 3.00 | 100.0 | 100.0 |
Obras de Drenaje | 26.00 | 19,045,674.79 | 26.00 | 100.0 | 100.0 | ||
Hopelchen-Bolonchen | 92+914 | 1.00 | 705,509.02 | 1.00 | 100.0 | 100.0 | |
Lim. Edos. Tab./Camp.-Escárcega y Escárcega-Lim. Edos. Camp./Q. Roo (T.A.) (12) | 5.00 | 5,897,624.26 | 5.00 | 100.0 | 100.0 | ||
Ramal Candelaria - Nuevo Coahuila (13) | 6.26 | 80.20 | 18.00 | 10,802,736.64 | 18.00 | 100.0 | 100.0 |
Ramal Palizada (14) | 11.64 | 37.50 | 2.00 | 1,639,804.87 | 2.00 | 100.0 | 100.0 |
Paraderos | 25.00 | 8,807,261.92 | 25.00 | 100.0 | 100.0 | ||
Ramal Candelaria - Nuevo Coahuila y Villahermosa - Escárcega (T.A.) (15) | 25.00 | 8,807,261.92 | 25.00 | 100.0 | 100.0 | ||
Reductores de Velocidad | 69.00 | 7,293,699.37 | 69.00 | 100.0 | 100.0 | ||
Reductores de Velocidad | 69.00 | 7,293,699.37 | 69.00 | 100.0 | 100.0 | ||
Mejoramiento de Seguridad Vial | 6.00 | 20,497,429.86 | 6.00 | 100.0 | 100.0 | ||
Entr. Sabancuy (Cd. del Carmen - Champotón) | 76+460 | 1.00 | 9,708,513.12 | 1.00 | 100.0 | 100.0 | |
Villahermosa-Escárcega y Escárcega-Champotón (T.A.) (16) | 5.00 | 10,788,916.74 | 5.00 | 100.0 | 100.0 | ||
Conservación Periódica de Puentes | 3.00 | 7,880,905.90 | 3.00 | 100.0 | 100.0 | ||
Conservación Rutinaria de Tramos | 1,375.96 | 115,881,543.67 | 1,375.96 | 100.0 | 100.0 | ||
Señalamiento Horizontal | 864.71 | 26,992,320.97 | 864.71 | 100.0 | 100.0 | ||
Barrera de Protección | 3,948.00 | 2,876,363.87 | 3,948.00 | 100.0 | 100.0 | ||
Señalamiento Vertical | 6,777.00 | 28,998,452.90 | 6,777.00 | 100.0 | 100.0 | ||
Conservación Rutinaria de Puentes | 161.00 | 9,192,195.68 | 161.00 | 100.0 | 100.0 | ||
Estudios y/o Proyectos | 2.00 | 11,391,812.36 | 2.00 | 100.0 | 100.0 | ||
(1) Del km 6+000 al km 9+000 y del km 10+500 al km 12+500 | |||||||
(2) Del km 20+000 al km 21+500 y del km 30+000 al km 32+500 | |||||||
(3) Del km 90+000 al km 92+319, del km 92+630 al km 93+316, del km 93+454 al km 94+032, del km 94+230 al km 94+410, del km | |||||||
94+588 al km 94+965, del km 95+140 al km 96+000 | |||||||
(4) Del km 105+000 al km 106+300, del km 106+550 al km 107+300 y del km 107+550 al km 109+000 | |||||||
(5) Del km 196+940 al km 197+760, del km 197+940 al km 198+215, del km 198+370 al km 198+845, del km 199+752 al km 200+062, | |||||||
del km 200+265 al km 203+540, del km 204+150 al km 204+295, del km 205+000 al km 205+820, del km 206+460 al km 207+770 | |||||||
del km 207+860 al km 207+990, del km 208+100 al km 208+740, y del km 211+200 al km 215+000. | |||||||
(6) Del km 4+000 al km 19+700, del km 20+200 al 21+000, del km 21+900 al 26+600 | |||||||
(7) Del km 274+100 al km 274+730, del km 275+800 al km 276+100, del km 276+400 al km 276+650, del km 277+400 al km 277+650, | |||||||
del km 277+892 al km 278+006, del km 278+248 al km 278+323, del km 279+800 al km 280+050, del km 281+280 al km 281+585, | |||||||
del km 282+400 al km 282+600, del km 284+800 al km 285+650, del km 285+910 al km 286+800, del km 287+050 al km 288+00 | |||||||
del km 288+600 al km 290+316 y del km 295+000 al km 295+880 | |||||||
(8) Del Km 27+000 al km 35+159.40 de la carretera Escarcega - Chetumal, del km 45+300 al km 50+000 y del km 79+000 al km | |||||||
88+000 de la carretera Cd. del Carmen - Campeche; del Km 41+000 al km 46+000 y del km 75+018 al km 77+250 de la carretera | |||||||
Escarcega - Champoton; del km 11+700 al km 15+500 y del km 16+500 al km 18+000 de la carretera Haltunchen - Cayal; y del km | |||||||
52+000 al km 57+000 de la carretera Chencolli - Lim. Edos. Camp./Yuc, con esto se atendio una longitud de 39.39 km con un | |||||||
área de 389,699.22 m2 | |||||||
(9) Del km 16+485 al km 16+760, del km 17+475 al km 17+500, del km 76+950 al km 77+100, del km 83+300 al km 83+423, del km | |||||||
103+900 al km 104+160, del km 107+640 al km 107+690, y del km 109+298 al km 109+415. | |||||||
(10) del km 161.381 al km 162.200 | |||||||
(11) Del km 64+374 al km 65+600, del km 66+000 al km 66+140, del km 66+215 al km 66+356, del km 66+860 al km 66+950, del k | |||||||
67+245 al km 68+058, del km 68+760 al km 69+200, y del km 71+100 al km 71+250 | |||||||
(12) Km 200+153, Km 205+166, Km 211+840, y KM 273+350, del tramo Lim. Edos. Tab./Cam. - Escárcega; y Km 163+820 del tramo | |||||||
Escárcega - Lim. Edos. Cam./Q. Roo. | |||||||
(13) Km 6+269, Km 7+089, Km 7+609, Km 8+170, Km 8+831, Km 10+966, Km 11+137, Km 12+064, Km 12+305, Km 12+963, Km 14+762, | |||||||
Km 15+321, Km 69+235, Km 70+753, Km 72+160, Km 73+396, Km 76+311, y Km 80+197 | |||||||
(14) Km 33+152 y Km 37+502 | |||||||
(15) Km 2+485, Km 2+700, Km 2+800, Km 16+500, Km 16+510, Km 23+300, Km 23+310, Km 23+700, Km 23+710, Km 31+200, Km 34+10 | |||||||
Km 34+110, Km 39+800, Km 44+370, Km 49+900, Km 53+850, Km 58+250, Km 61+775, Km 73+060, y Km 73+900 de la carretera | |||||||
Ramal a Candelaria - Nuevo Coahuila, Km 210+770, Km 225+755, Km 231+550, Km 236+020, y Km 250+000 de la carretera | |||||||
Escárcega - Villahermosa. | |||||||
(16) Entronque "Palizada" en el km 155+510; entronque "División del Norte" en el km 294+980; Entronque "El Chinal" en el km 210+7 | |||||||
de la carretera Villahermosa Escárcega; entronque "Ulumal - Carrillo Puerto" en el km 78+200, y entronque "Dzacabuchen" | |||||||
en el km 77+560, de la carretera Escárcega - Champotón. |