SUBSECRETARIA DE INFRAESTRUCTURA | ||||||||
DIRECCION GENERAL DE CONSERVACION DE CARRETERAS | ||||||||
Programa Nacional de Conservación de Carreteras | ||||||||
DICIEMBRE 2017 | ||||||||
No. | NOMBRE DE LA OBRA | UBICACIÓN | META | ASIGNACIÓN | AVANCE FÍSICO | AVANCE FINANCIERO |
||
Inicial | Final | UNIDAD | % | |||||
HIDALGO | 147,848,595.00 | 100.0 | 99.7 | |||||
RECONSTRUCCIÓN | 1,600,000.00 | 1.00 | 100.0 | 99.9 | ||||
Reconstrucción de puentes | 1.00 | 1,600,000.00 | 1.00 | 100.0 | 99.9 | |||
1 | P.P. Acayuca (Tizayuca II - Pachuca) | 75+500 | 1.00 | 1,600,000.00 | 1.00 | 100.0 | 99.9 | |
Conservación Periódica | 36.00 | 66,500,379.00 | 36.00 | 100.0 | 99.5 | |||
Carpeta de 5.0 cm | 11.30 | 18,743,904.00 | 11.30 | 100.0 | 99.3 | |||
2 | T Colonias-T Portezuelo (Cpo. A) | 14.0 | 18.0 | 4.00 | 6,000,000.00 | 4.00 | 100.0 | 100.0 |
3 | T Colonias-T Portezuelo (Cpo. B) | 12.5 | 16.0 | 3.50 | 7,800,000.00 | 3.50 | 100.0 | 100.0 |
4 | Pachuca-Lim. Edos. Hgo./Ver | 18.2 | 22.0 | 3.80 | 4,943,904.00 | 3.80 | 100.0 | 97.3 |
Bacheo y Carpeta de 5.0 cm | 20.00 | 34,818,469.00 | 20.00 | 100.0 | 99.6 | |||
5 | T Colonias-T Portezuelo (Cpo. A) | 8.0 | 14.0 | 6.00 | 10,691,475.00 | 6.00 | 100.0 | 98.7 |
6 | T Colonias-T Portezuelo (Cpo. A) | 23.0 | 27.0 | 4.00 | 7,511,762.00 | 4.00 | 100.0 | 100.0 |
7 | T Colonias-T Portezuelo (Cpo. B) | 28.0 | 32.0 | 4.00 | 7,510,000.00 | 4.00 | 100.0 | 100.0 |
8 | T. Portezuelo - Lím. de Edos. Hgo./S.L.P. | 123.0 | 129.0 | 6.00 | 9,105,232.00 | 6.00 | 100.0 | 100.0 |
Recuperación y Carpeta de 5.0 cm | 4.70 | 12,938,006.00 | 4.70 | 100.0 | 99.6 | |||
9 | T Colonias-T Portezuelo (Cpo. A) T.A. | 27.0 | 32.0 | 4.70 | 12,938,006.00 | 4.70 | 100.0 | 99.6 |
Conservación Rutinaria de Tramos | 1,014.57 | 61,066,398.00 | 1,014.57 | 100.0 | 99.9 | |||
10 | Venta de Carpio-Pitula | 51+000 | 83+400 | 83.60 | 4,180,400.00 | 83.60 | 100.0 | 100.0 |
11 | Pachuca-Cd. Sahagún | 7+800 | 45+490 | 92.88 | 4,996,000.00 | 92.88 | 100.0 | 100.0 |
12 | Pachuca-Lim. Edos. Hgo./Pue. | 10+200 | 82+900 | 94.18 | 4,368,300.00 | 94.18 | 100.0 | 100.0 |
13 | México-Pachuca | 54+600 | 78+300 | 44.18 | 2,589,900.00 | 44.18 | 100.0 | 100.0 |
14 | T Colonia-T Portezuelo | 8+200 | 32+000 | 47.60 | 3,179,900.00 | 47.60 | 100.0 | 99.9 |
15 | Pachuca-Lim. Edos. Hgo./Qro. | 0+000 | 71+660 | 94.78 | 5,401,600.00 | 94.78 | 100.0 | 100.0 |
16 | T Colonia-T Portezuelo | 37+000 | 81+000 | 88.00 | 5,024,900.00 | 88.00 | 100.0 | 100.0 |
17 | Jorobas-Tula | 5+500 | 30+000 | 49.00 | 2,857,700.00 | 49.00 | 100.0 | 99.9 |
18 | T Portezuelo-Lim. Edos. Hgo./SLP | 81+000 | 166+000 | 85.00 | 5,158,200.00 | 85.00 | 100.0 | 100.0 |
19 | T Portezuelo-Lim. Edos. Hgo./SLP | 166+000 | 251+900 | 85.90 | 5,508,200.00 | 85.90 | 100.0 | 100.0 |
20 | Pachuca-Lim. Edos. Hgo./Ver. | 4+500 | 75+000 | 87.52 | 4,998,200.00 | 87.52 | 100.0 | 100.0 |
21 | Pachuca-Lim. Edos. Hgo./Ver. | 75+000 | 155+000 | 80.00 | 4,910,300.00 | 80.00 | 100.0 | 100.0 |
22 | Pachuca-Lim. Edos. Hgo./Ver. | 155+000 | 212+500 | 81.93 | 4,660,923.00 | 81.93 | 100.0 | 99.5 |
Conservación Rutinaria de Tramos (Alcantarillas) | 3.00 | 1,200,000.00 | 3.00 | 100.0 | 100.0 | |||
Gastos de Operación | SM | 2,031,875.00 | 98.8 | |||||
Señalamiento Horizontal | 1,012.28 | 5,000,000.00 | 1,012.28 | 100.0 | 100.0 | |||
Señalamiento Horizontal | 1,012.28 | 5,000,000.00 | 1,012.28 | 100.0 | 100.0 | |||
Barrera de Protección | 3,298.00 | 3,000,000.00 | 3,298.00 | 100.0 | 99.9 | |||
Barrera de Protección | 3,298.00 | 3,000,000.00 | 3,298.00 | 100.0 | 99.9 | |||
Señalamiento Vertical | 1,085.00 | 3,000,000.00 | 1,085.00 | 100.0 | 99.7 | |||
Señalamiento Vertical | 1,085.00 | 3,000,000.00 | 1,085.00 | 100.0 | 99.7 | |||
Conservación Rutinaria de Puentes | 135.00 | 3,681,818.00 | 135.00 | 100.0 | 100.0 | |||
Conservación Rutinaria de Puentes | 135.00 | 3,681,818.00 | 135.00 | 100.0 | 100.0 | |||
OTROS SUBPROGRAMAS | 1.00 | 4,000,000.00 | 1.00 | 100.0 | 100.0 | |||
Estudios y Proyectos de Tramos | 1.00 | 4,000,000.00 | 1.00 | 100.0 | 100.0 |